DCSIMG

Planned roadworks in the North West, August 11-17

The M6 south of junction 35 Carnforth.

The M6 south of junction 35 Carnforth.

The following summary of planned new and ongoing road improvements over the coming week is correct as of Friday 8 August and could be subject to change due to weather conditions or unforeseen circumstances. All improvement work is carried out with the aim of causing as little disruption as possible.

M6 Junction 16 Barthomley

Overnight work is underway to reduce congestion and improve traffic flow at junction 16 of the M6. The scheme will provide a third lane on the north and southbound exit slip roads and the approach on the A500. Additional traffic lights will also be installed. There will be some overnight closures of slip roads and the A500 and B5078 at different stages of the project. A temporary speed limit of 50mph is also in place, and the project is expected to be completed by the middle of December.

M6 Junctions 20 to 21 Thelwall Viaduct

Work on the Thelwall Viaduct has almost been completed, and the temporary contraflow lane, 40mph speed limit and narrow lanes have now been removed. Joint replacement work on the viaduct is still required on the northbound exit slip road at junction 21 but this will be limited to occasional overnight lane and slip road closures at weekends.

M56 Junction 12 Runcorn to Junction 14 Hapsford

Work is taking place to resurface the westbound carriageway of the M56 between Junction 12 Runcorn to Junction 14 Hapsford. The work will also include the replacement of worn roadmarkings on the eastbound carriageway.

All of the resurfacing will be done overnight between 10pm and 5am, Mondays to Fridays. To do this safely the motorway will be reduced to single lane running overnight in one direction between the two junctions with some overnight closures of the M56 Westbound access junction. A clearly signed diversion will be in place. During the day drivers may also notice some hard shoulder closures associated with the work.

M60 Junction 8 Sale to M62 Junction 20 Rochdale

A major project is taking place to cut congestion and improve journey times on parts of the M60 and the M62 in Greater Manchester.

The first stage of the project will see engineers carry out site surveys and ground investigation work. Some sections of the hard shoulder will be closed although vehicles will be able to get through the cones in an emergency.

A temporary steel barrier to protect road workers will be installed in the hard shoulder between junction 18 of the M62 at the M60/M66 interchange and junction 20 at Rochdale. At the same time, a 50mph speed limit will be introduced on the M62 section, to ensure the safety of the workforce and motorists.

The temporary speed limit, enforced with temporary average speed cameras, will then gradually be extended across the length of the smart motorway route over the following weeks.

M60 Junction 24 Denton

Phase two of the Denton Island improvements is underway at junction 24 of the M60, where the motorway meets the M67 and the A57– a key commuter route into Manchester city centre. The whole project is due to be completed by Friday 19 December with most of the work carried out overnight. Some road and lane closures will be necessary.

A595 Crossbarrow

There will be daytime traffic signals for boundary fence renewals on the footpath / cycleway between 9.30am and 4.00pm from Monday 11 August to Sunday 31 August around the junction with Great Clifton. Pedestrians and cyclists may be asked to dismount and be escorted through the site at times. There will be a temporary 40mph speed limit past the roadworks.

A595 Parton

There will be daytime traffic signals in place to take down and rebuild sections of a collapsed wall from 9.00am to 4.00pm from Monday 11 August to Thursday 21 August.

 

Comments

 
 

Back to the top of the page